Railways approves 122 crore project to double Barbil-Bolanikhadan track for ore movement

Public and Policy Editorial DeskUpdated 28 Sep 20263 min readSource: PIBHow we report

Indian Railways has approved a 122 crore rupee investment to double 6 kilometres of track between Barbil and Bolanikhadan on the South Eastern Railway network. The project aims to increase freight handling capacity on a key corridor used primarily for movement of iron ore and related mineral products.

The Barbil-Bolanikhadan section currently operates as a single line and forms part of the Energy, Mineral and Cement Corridor identified by Indian Railways for infrastructure strengthening. The doubling will enable smoother and faster movement of trains carrying ore and reduce operational bottlenecks on this busy freight route.

Key facts

  • Project cost: 122 crore rupees
  • Track length to be doubled: 6 kilometres
  • Current freight capacity: approximately 9 million tonnes per annum (MTPA)
  • Additional capacity after doubling: 8.9 MTPA
  • Current traffic: about 6 loaded trains per day of originating iron ore
  • Railway zone: South Eastern Railway
  • Primary freight: high-grade iron ore and pellets from SAIL’s Bolani mines and private sidings operated by Rungta and Khatau Narbheram companies
  • Destination: major steel plants and ports

Why the doubling is needed

The single-line section between Barbil and Bolanikhadan currently carries around 9 million tonnes of iron ore annually. This comprises approximately 6 loaded trains per day originating from SAIL’s Bolani mines and private mining operations. The traffic moves high-grade ore and iron ore pellets to steel manufacturing plants and port terminals.

As mining operations in the region expand and steel plants increase their production capacity, the existing single track will become a constraint. Mining companies and industrial users have plans to boost output from mines and port facilities in coming years. Without additional track capacity, trains would face delays and congestion, preventing the smooth flow of minerals to their destinations.

What doubling a railway line means

Doubling involves laying a second parallel track alongside the existing single line. This allows trains to move in both directions simultaneously and increases the total number of trains that can be handled on that section. Instead of scheduling trains to move one after another with gaps between them, doubled sections permit more frequent and continuous traffic flow.

Expected benefits

After the project is completed, the section can handle an additional 8.9 million tonnes per annum of freight. This will bring total capacity on the 6 kilometre stretch to approximately 17.9 million tonnes annually, nearly double the current level.

The doubling will reduce train delays on this corridor, allowing iron ore and pellet movements to operate on more predictable schedules. This benefit extends to steel plants and ports that depend on regular shipments. The project also supports the broader objective of strengthening the Energy, Mineral and Cement Corridor, which is critical for India’s industrial supply chains.

By completing this doubling work before the full expansion of mine capacity and port facilities takes place, Indian Railways aims to prevent future bottlenecks. This proactive approach avoids scenarios where industrial capacity exists but rail infrastructure cannot support the required freight volumes.

What this means for you

For steel industry workers and consumers, this project supports stable ore supplies to manufacturing plants, which helps maintain production and employment. For mining companies, improved rail capacity reduces waiting times and shipping costs. For port cities receiving ore exports, better track capacity means more predictable cargo handling and business planning.

Citizens in regions dependent on steel production and mineral exports will see indirect benefits through more efficient supply chains. The investment also reflects government commitment to railway infrastructure in mineral-rich states, particularly Odisha, where the Barbil-Bolanikhadan section is located.

Leave a Comment